Typical Kitchen Renovation: 8-12 Weeks
A full kitchen renovation typically takes 8-12 weeks from demolition to completion. Here's what to expect.
Week 1-2: Demolition and Rough Work
- Existing cabinets, counters, and flooring removed
- Walls opened for inspection
- Any structural changes made
- Dust barriers installed
Week 3-4: Rough Mechanical
- Electrical rough-in for new outlets and lighting
- Plumbing rough-in for sink, dishwasher, ice maker
- HVAC adjustments if needed
- Inspections by city
Week 5-6: Walls and Flooring
- Drywall installed and finished
- Painting primer coats
- Flooring installation
Week 7-8: Cabinets and Countertops
- Cabinet installation (2-3 days)
- Countertop template (after cabinets)
- Countertop fabrication (1 week)
- Countertop installation
Week 9-10: Finish Work
- Backsplash installation
- Plumbing fixtures installed
- Electrical fixtures and outlets
- Appliance installation
Week 11-12: Final Details
- Final paint touch-ups
- Hardware installation
- Final inspections
- Walkthrough and punch list
What Would Your Project Cost?
Get an instant cost range for your ZIP code and see licensed contractors near you. Free, no signup required.
Get My Free EstimateGet contractor pricing for your area
Enter your email and we'll send you cost data and licensed contractor matches near you.